Refund of retention money for the BUNC project.
This record consists of general correspondence from Next spaces Ltd. regarding the refund of retention money of BRACU new campus project.
| Main Author: | Next spaces Ltd. |
|---|---|
| Format: | General correspondence |
| Language: | English |
| Published: |
Brac University
2023
|
| Subjects: | |
| Online Access: | http://hdl.handle.net/10361/20812 |
Similar Items
-
Regarding refund of retention money for BRACU new campus project
by: Brac University
Published: (2023) -
Releasing 50% of retention money of the main contract
by: Brac University
Published: (2023) -
Application for the refund of the temporary substation fee returned by DESCO
by: BUCG-ABC Joint Venture
Published: (2023) -
Releasing 50% of retention money of the main contract of BRAC University new campus project
by: Brac University
Published: (2023) -
Request for releasing 50% of retention money of the main contract of BRAC University new campus project
by: BUCG-ABC Joint Venture (BUCG-ABC JV)
Published: (2023)